11. The Standard Service is generally divided into 6 work stages

Purchase cart Previous page Return to chapter overview Next page

 

The essential functions of each work stage relevant to the service are identified hereafter as follows:

 

Stage 1: Inception

(a) Receive, appraise and report on the client's requirements with regard to the client's brief;
(b) Determine the site and rights and constraints;
(c) Determine budgetary constraints;
(d) Determine the need for consultants;
(e) Determine indicative project timelines;
(f) Determine methods of contracting; and
(g) whether other statutory authority applications are required or desirable.

 

Stage 2: Concept and viability (concept design)

(a) Prepare an initial design concept and advise on:
(i) the intended space provisions and planning relationships;
(ii) proposed materials and intended building services; and
(iii) the technical and functional characteristics of the design.
(b) Check for conformity of the concept with the rights to the use of the land.
(c) Consult with local and statutory authorities.
(d) Review the anticipated costs of the project.
(e) Review the project programme.

 

Stage 3: Design Development

(a) Develop all aspects of the design from concept to full development, including but not limited to, construction systems, materials, fittings, and finishes selections;
(b) Review the programme and budget with the client, principal consultant or other consultants;
(c) Coordinate other consultants designs into building design;
(d) Prepare design development drawings including drafting technical details and material specifications;
(e) Discuss and agree on the building plan approval requirements with the local authority;

 

Stage 4: Documentation and procurement

 

Stage 4.1

(a) Prepare documentation required for local authority building plan application submission;
(b) Co-ordinate technical documentation with the consultants and complete primary co-ordination sufficient to support building plan submission;
(c) Review the costing and programme with the consultants;
(d) Obtain the client's authority, and submit documents for approval at the local authority.

 

Stage 4.2

(a) Prepare specifications for the works;
(b) Complete technical documentation sufficient for tender;
(c) Obtain offers for the execution of the works;
(d) Evaluate offers, and recommend a successful tenderer for appointment;
(e) Prepare the contract documentation and arrange the signing of the building contract by the client and the successful tenderer;
(f) Complete remaining technical documentation and coordinate same with the consultants;

 

Stage 5: Construction

(a) Administer the building contract;
(b) Give possession of the site to the contractor;
(c) Issue construction documentation;
(d) Review sub-contractor designs, shop drawings and documentation for conformity of design intent;
(e) Inspect the works for conformity with the contract documentation and acceptable quality in terms of industry standards;
(f) Administer and perform the duties and obligations assigned to the principal agent in the building contract;
(g) Manage the completion process of the project;
(h) Assist the client to obtain the required documentation necessary for the client to obtain the occupation certificate.

 

Stage 6: Close-out

(a) Facilitate the project close-out including the preparation of the necessary documentation to effect completion, handover and operational manual of the project.
(b) When the contractor's obligations with respect to the building contract have been fulfilled, the architectural professional shall issue the certificates related to the contract completion.
(c) Provide the client with construction record documentation and the relevant technical and contractual undertakings by the contractor and subcontractors.