Electricity Regulation Act, 2006 (Act No. 4 of 2006)

Chapter I : Interpretation

2A. Application of Act

Purchase cart Previous page Return to chapter overview Next page

 

(1) This Act is applicable to the generation, transmission, distribution, reticulation, system operation, trading, and import and export, of electricity activities, and to persons undertaking such activities.

 

(2) The Act is not applicable to the operation of generation facilities with or without battery storage—
(a) for the sole purpose of providing standby or back-up electricity;
(b) where the facility, irrespective of capacity (megawatts), does not have a point of connection to the facility; or
(c) with a capacity of not more than 100 kilowatts, which complies with the code, has a point of connection and is subject to the distributor’s prescribed conditions relating to the continued use of the point of connection.

 

(3) For the purposes of subsection (2), the Regulator shall prescribe the manner in which the distributor shall keep a register of each facility.

 

[Section 2A inserted by section 3 and 31(a) of the Electricity Regulation Amendment Act, 2024, Notice No. 5139, GG51100, dated 20 August 2024 - effective 1 January 2025 per Proclamation Notice 236 of 18 December 2024 with exceptions]