Electricity Regulation Act, 2006 (Act No. 4 of 2006)

Notices

Integrated Resource Plan 2019

4. Input Parameter Assumptions

4.3 Installed and Committed Capacity

Purchase cart Previous page Return to chapter overview Next page

 

Installed capacity assumed in the IRP Update includes both Eskom and private generation (generation for own use and municipal generation) as filed and licensed with NERSA.

 

A list of Eskom and private and municipal generators, as licensed with NERSA, is included in Appendix A.

 

In line with the planned capacity in the promulgated IRP 2010–2030 and in accordance with Section 34 of the Electricity Regulation Act No. 4 of 2006, the Minister of Energy has, to date, determined that 39 730 MW of new generation capacity must be developed.

 

Of the 39 730 MW determined, about 18 000 MW has been committed8 to date. This new capacity is made up of 6 422 MW under the REIPPP with a total of 3 876 MW operational on the grid. Under the committed Eskom build, the following capacity has been commissioned: 1 332 MW of Ingula pumped storage, 2 382 MW of Medupi (out of the 4 800 MW planned), 800 MW of Kusile (out of the 4 800 MW planned) and 100 MW of Sere Wind Farm. 1 005 MW from OCGT for peaking has also been commissioned.

 

For the IRP Update analysis, the remaining units at Medupi and Kusile were assumed to come on line as indicated in Table 3.

 

Table 3: CODs for Eskom New Build

 

Medupi

Kusile

Unit 6

Commercial operation

Unit 1

Commercial operation

Unit 5

Commercial operation

Unit 2

April 2019

Unit 4

Commercial operation

Unit 3

January 2020

Unit 3

June 2019

Unit 4

January 2021

Unit 2

June 2019

Unit 5

September 2021

Unit 1

December 2019

Unit 6

July 2022

 

4.3.1 Existing Eskom Plant Performance

 

The existing Eskom’s generation plant energy availability factor (EAF) was assumed to be averaging 86% in the promulgated IRP 2010–2030. The actual EAF at the time was averaging 85%. Since then, Eskom’s EAF declined steadily to a low average of 71% in the 2015/16 financial year before recovering to average around 77.% in the 2016/17 financial year. Information as at January 2018 indicates that EAF has regressed further to levels below 70%. This low EAF was the reason for constrained capacity early in December 2018 and January 2019 that resulted in load shedding.

 

Eskom’s existing generation plant will still dominate the South African electricity installed capacity for the foreseeable future. The current and future performance of these Eskom plants is critical for security of supply and heavily influences the capacity planned to be introduced under the IRP.

 

As part of the comments process on the draft IRP 2018, Eskom submitted revised system availability projections per power station. The submission contains two scenarios of which scenario 1 and scenario 2 project an average EAF of 80% by 2030 and 75% by 2030, respectively.

 

Plant performance projections in the final plan contained in this report are based on the scenario with EAF of 75% by 2030. In this scenario, EAF starts at 71% in year 2020, and increases to 75.5% by year 2025 and beyond (see Appendix A).

 

4.3.2 Existing Eskom Plant Design Life

 

Existing generation plant life is a major consideration in the IRP as it will affect supply and demand balance. The IRP considers both Eskom and non-Eskom plants (municipal and large private sector plants) in this regard.

 

Eskom coal plants were designed and built for a 50-year life, which falls within the 2050 study period of the IRP 2018 update.

 

Eskom has also submitted a revised plant end of design life (decommissioning) plan. This submission brings forward the shutdown of some units at Grootvlei, Komati and Hendrina.

 

Figure 7 shows that about 5 400 MW of electricity from coal generation by Eskom will be decommissioned by year 2022, increasing to 10 500 MW by 2030 and 35 000 MW by 2050. The revised decommissioning schedule is attached in Appendix A.

 

N1360 Figure 7 Cumulative Eskom Coal Generation Plants Decommissioning

 

The socio economic impact of the decommissioning of these Eskom plants has not been quantified or included in this IRP.

 

It is also expected that by year 2024, 1 800 MW of nuclear power generation (Koeberg) will reach end-of-life. Eskom has initiated preparations and processes to extend the life of this plant to 2044, subject to the necessary regulatory approvals. In light of the projected lower EAF for Eskom coal power plants, the IRP plan is based on the assumption that Koeberg plant life would be extended to 2044.

 

Mitigation of the risks associated with the adopted assumption is included in the risk section of this report.

 

4.3.3 Compliance with Minimum Emissions Standards (Air Quality Regulations)

 

A number of Eskom power plants (Majuba, Tutuka, Duvha, Matla, Kriel and Grootvlei) have been retrofitted with emission abatement technology to ensure compliance with the law (viz. National Environmental Management Act: Air Quality, 2004 or NEMA).

 

In 2014 Eskom applied for postponement of the date for compliance and permission in this regard was granted for a period not exceeding 5 years. To date, Grootvlei is the only station that has been brought to compliance and this failure to undertake abatement retrofits is likely to result in non-compliant plants becoming unavailable for production from year 2020, unless further postponement is granted. Eskom is in the process of applying for further postponement in line the provisions of the law.

 

In light of projected lower EAF, the assumption adopted in the IRP is that NEMA-affected Eskom coal plant will remain available for production.

 

________________________________________

8 Committed refers to the capacity commissioned or procured and officially announced by the Minister of Energy.