Electricity Regulation Act, 2006 (Act No. 4 of 2006)RegulationsElectricity Regulations on New Generation Capacity, 20118. Cross border projects |
(1) | Where a section 34(1) determination requires or contemplates that new generation capacity be established through a cross border project, as contemplated in regulation 6(4), the applicable IPP procurement programme may, but need not necessarily, have the sole purpose of procuring new generation capacity from beyond the borders of the Republic. |
(2) | The procurement process in respect of a cross border project shall be conducted with due regard to any agreements, memoranda of understanding or arrangements referred to in regulation 6(4). |
[Subregulation 8(2) substituted by regulation 6 of Notice No. R. 1366 of 2016]