Infrastructure Development Act, 2014 (Act No. 23 of 2014)SchedulesSchedule 2 (Section 17(2)) |
SCHEDULE 2
Process and periods of time
1. |
Period for submitting application and project plan measured from approval by steering committee of project plan. |
7 days |
2. |
Period for public consultation on the application and project plan. |
30 days |
3. |
Period for application and project plan to be amended and submitted to the relevant authority for consideration and approval. |
52 days |
4. |
Period for submission to the relevant authority of detailed development and mitigation plan based on an approved project plan |
60 days |
5. |
Period for public consultation on the development and mitigation plan and review by relevant authority. |
44 days |
6. |
Period for relevant authority to consider and assess development and mitigation plan and make final regulatory decision. |
57 days |