Infrastructure Development Act, 2014 (Act No. 23 of 2014)

Schedules

Schedule 2 (Section 17(2))

Purchase cart Previous page Return to chapter overview Next page

 

SCHEDULE 2

Section 17(2)

 

Process and periods of time

 

1.

Period for submitting  application and project plan measured from approval by steering committee of project plan.

7 days

2.

Period for public consultation on the application and project plan.

30 days

3.

Period for application and project plan to be amended and submitted to the relevant authority for consideration and approval.

52 days

4.

Period for submission to the relevant authority of detailed development and mitigation plan based on an approved project plan

60 days

5.

Period for public consultation on the development and mitigation plan and review by relevant authority.

44 days

6.

Period for relevant authority to consider and assess development and mitigation plan and make final regulatory decision.

57 days