A Joint Steering Committee is responsible for the implementation of a joint programme and should -

a)develop plans and strategies for the implementation of the joint programme;
b)compile and submit regular progress reports to -
i)the executive authority of the coordinating department; and
ii)the Joint Panel of Executive Authorities; and
c)assist the joint programme manager in performing any of the functions of joint programme manager proposed in clause 7(2).