Construction Regulations, 2014

22. Cranes

Purchase cart Previous page Return to chapter overview Next page

 

A contractor must, in addition to compliance with the Driven Machinery Regulations, 1988 ensure that where tower cranes are used—

(a)they are designed and erected under the supervision of a competent person;
(b)a relevant risk assessment and method statement are developed and applied;
(c)the effects of wind forces on the crane are taken into consideration and that a wind speed device is fitted that provides the operator with an audible warning when the wind speed exceeds the design engineer's specification;
(d)the bases for the tower cranes and tracks for rail-mounted tower cranes are firm, level and secured;
(e)the tower crane operators are competent to carry out the work safely; and
(f)the tower crane operators have a medical certificate of fitness to work in such an environment, issued by an occupational health practitioner in the form of Annexure 3.