Petroleum Pipelines Act, 2003 (Act No. 60 of 2003)Chapter 3 : Licences19. Finalisation of application |
(1) | The Authority must decide on an application within 60 days after— |
(a) | the expiration of the period contemplated in section 17(2)(d), if no objections have been received; or |
(b) | receiving the response of the applicant as contemplated in section 18(c). |
(2) | The Authority must provide the applicant with a copy of its decision as well as a list of the factors on which the decision was based. |
(3) | The Authority may issue separate or combined licences for— |
(a) | the construction of petroleum pipelines or pipeline systems, loading facilities and storage facilities; and |
(b) | the operation of petroleum pipelines or pipeline systems, loading facilities and storage facilities |